2014
Corrimal Coke Works ceases operation
2014 – 2017
Planning and consultation for future use of site
October 2017
ICC submits Planning Proposal to Wollongong City Council
April 2018
Wollongong City Council endorses Planning Proposal to proceed for Gateway Determination
August 2018
Department of Planning & Environment issues a Gateway Determination confirming the rezoning can proceed
September 2018 – April 2019
Completion of further technical studies
Ongoing community consultation
May 2019
Updated Planning Proposal submitted to Wollongong City Council
Mid 2019 – Mid 2020
Wollongong City Council considers updated Planning Proposal
ICC and Legacy Property continue to provide further information to address Council queries
October 2020
Wollongong City Council resolves to seek changes to Planning Proposal
November 2021 – March 2021
ICC and Legacy Property respond to Council decision
April 2021
Wollongong City Council resolves to place Planning Proposal on public exhibition
June – August 2021
Formal public exhibition for 60 day period
Late 2021
Wollongong City Council reviews public submissions
Final report to Department of Planning, Industry and Environment
WE ARE HERE
Late 2021/Early 2022
Gazettal of rezoning
2022 Onwards
Development applications
Site preparation works including remediation and bulk earthworks
Construction of new roads, parks and dwellings